Thursday, December 13, 2012

Saturday, December 8, 2012

Console and Gobos Move In - Tranquility On Studios

Gobos Completed for The Studio

Punch block being wired for the Furman Headphone System 

Console Moves into The Control Room 

Friday, December 7, 2012

Tranquility One Studios - Construction Update

Shelf Lighting Installed along with cans for back of the Control Room

Cloud getting prepared to be hung - carpet installed

Cloud in place along with the lighting

Thursday, December 6, 2012

Another Update - Tranquility One Studios

Floor Installed in front and under console

Monday, December 3, 2012

More work on the Control Room - Tranquility One Studios


Acoustic Cloud gets built to hang over mix position


Control Room Glass Installed

Electrical completed - Dimmers and outlets installed

Treatment on the control room front wall completed

Thursday, November 29, 2012

Another Studio Update - Tranquility One

Wall Treatment Getting Installed for the Control Room












































Ceiling Treatment Installed for the Control Room

Sunday, November 25, 2012

Studio Construction Update - Iso Room Doors

Doors between the control room and isolation booth installed

Friday, November 23, 2012

Studio Construction Update - Control Room Ceiling Acoustic Shelf

Control Room Ceiling - Completed Acoustic / Lighting Shelf

Sunday, November 18, 2012

The Garden - Brussels Sprouts

Last from the Garden for this year!

Thursday, November 15, 2012

Studio Progress - The Control Room

Acoustic / Lighting Shelf - Drywall completed on the control room side wall

Control Room back wall

Tuesday, November 13, 2012

Studio Update - Tranquility One

Microphone stands and outboard gear racks are starting to arrive

Drywall and recessed lighting installed over client couch area

Add caption

Thursday, November 8, 2012

Tranquility One Studios - Another Update

Diffuser / Indirect Lighting Shelf added to Control Room

Wraps around the back and side walls

Saturday, November 3, 2012

Tranquility One Studios - Construction Update


Ceiling of Control Room Gets Drywall

2 Layers of 5/8

Thursday, October 25, 2012

Another Construction Update: Tranquility One Studios


2nd layer of drywall completed on the control room walls











































Drywall begins on the ceiling of the control room

Tuesday, October 23, 2012

Tranquility One Studios - Update: ProTools System

More pieces of the ProTools system arrived - Sync I/O

Saturday, October 20, 2012

Friday, October 19, 2012

Tranquiity One Studios - Construction Update

Control Room Front wall

View of Control Room Through Iso Booth

Outer wall of the Iso Booth

Thursday, October 18, 2012

Studio Update - ProTools

The parts of The ProTools system are starting to arrive - 192 I/O Interface

Monday, October 15, 2012

Sunday, October 14, 2012

Drywall Begins - Tranquility One Studios

First layer of 5/8 drywall begins on the inner control room walls