Thursday, November 29, 2012

Another Studio Update - Tranquility One

Wall Treatment Getting Installed for the Control Room












































Ceiling Treatment Installed for the Control Room

Sunday, November 25, 2012

Studio Construction Update - Iso Room Doors

Doors between the control room and isolation booth installed

Friday, November 23, 2012

Studio Construction Update - Control Room Ceiling Acoustic Shelf

Control Room Ceiling - Completed Acoustic / Lighting Shelf

Sunday, November 18, 2012

The Garden - Brussels Sprouts

Last from the Garden for this year!

Thursday, November 15, 2012

Studio Progress - The Control Room

Acoustic / Lighting Shelf - Drywall completed on the control room side wall

Control Room back wall

Tuesday, November 13, 2012

Studio Update - Tranquility One

Microphone stands and outboard gear racks are starting to arrive

Drywall and recessed lighting installed over client couch area

Add caption

Thursday, November 8, 2012

Tranquility One Studios - Another Update

Diffuser / Indirect Lighting Shelf added to Control Room

Wraps around the back and side walls

Saturday, November 3, 2012

Tranquility One Studios - Construction Update


Ceiling of Control Room Gets Drywall

2 Layers of 5/8